Question - Batch encode (Task count Multiple CPU)
|
No.63558
|
Bikertrottle
( Mail / )
2010-08-29 06:15:55 ( ID:ziyyyfcap3. )
Bug or????
Try to encode 6 projects eaths containing multiple file's.
I set the "Task count" at 4 (have quad CPU)
1e project starts. After a while 2e project starts to a few % and then both stopped. Have to close the program.
After restart, set the "task count"at 1 and it works fine even with 12 projects.
Using HP Z400 3.2Ghz, Hypertreading On, Windows7 profesional,Videocard NVDIA FX3800
Rolf
( Mail / )
2010-09-06 21:28:26 ( ID:orp5shnh5aj )
I got the same issues.
|
Script written by TMPGEnc.
|